The new year is expected to bring the end of several major road projects in North Texas and the beginning of others.
In Carrollton, there will be planned panel replacements on Josey Lane throughout the year, said Jonathan Wheat, director of engineering for the city. There will also be panel replacements on Hebron Parkway from Marchant Boulevard to Marsh Lane in the fourth quarter of 2021.
The Sam Rayburn Tollway addition of a fourth lane in each direction is scheduled to be complete in late 2021, according to Michael Rey, North Texas Tollway Authority (NTTA) media relations manager.
Rey said the addition of a fourth lane in each direction on President George Bush Turnpike from Interstate 35E to Belt Line Road is scheduled to be complete in late 2021.