Eight weeks of I-295 ramp closures in Portland to begin March 15
Mon, 03/08/2021 - 6:15pm
PORTLAND — The City of Portland's Back Cove South Storage Facility project is entering its next phase of work, which is to connect the existing utilities (new or replaced) within the intersection of Marginal Way and Franklin Street to the new storage tanks under the Preble Street playing fields. As a result, there will be an approximate eight week period of alternating closures to the on and off ramps of the I-295 Exit 7 (Franklin St) interchange beginning March 15.
The City will be placing variable message boards with the latest ramp closure information in the vicinity of the work. The ramp closures will vary during the eight week timeframe so motorists should pay attention to the message boards or make plans to seek alternate routes during this time.

Related Keywords

Maine ,United States ,Back Cove ,City Of Portland , ,Maine Department Of Transportation ,Sargent Corporation ,Department Of Public Works ,Back Cove South Storage Facility ,Marginal Way ,Franklin Street ,Preble Street ,East End Wastewater Treatment ,Public Works ,Maine Department ,Memorial Day ,Sewer Overflow ,Diamond Street ,Portland Public Works ,Eight Weeks Ofi 295 Ramp Closures In Portland To Begin March 15 ,Work ,Commerce ,மைனே ,ஒன்றுபட்டது மாநிலங்களில் ,மீண்டும் கோவ் ,நகரம் ஆஃப் போர்டிலந்ட் ,மைனே துறை ஆஃப் போக்குவரத்து ,ஸார்‌ஜெஂட் நிறுவனம் ,துறை ஆஃப் பொது வேலை செய்கிறது ,மீண்டும் கோவ் தெற்கு சேமிப்பு வசதி ,விளிம்பு வழி ,பிராங்க்ளின் தெரு ,ப்ரேப்ளே தெரு ,கிழக்கு முடிவு கழிவு நீர் சிகிச்சை ,பொது வேலை செய்கிறது ,மைனே துறை ,நினைவகம் நாள் ,கழிவுநீர் ஓவர்‌ஃப்லோ ,வைரம் தெரு ,போர்டிலந்ட் பொது வேலை செய்கிறது ,வேலை ,வர்த்தகம் ,

© 2025 Vimarsana

comparemela.com © 2020. All Rights Reserved.