“There is going to be total closure of Third Mainland Bridge in order to allow for the casting of three number expansion joints on the Island Bound lane”
“The effective date of the closure will be from 12:00 midnight of 25th of December. So people will be allowed to use the Third Mainland Bridge to celebrate Christmas.
“By the time the Christmas is winding down which is 12:00 midnight, we are going to close it so that we will be able to cast the concrete on Saturday the 26th and 27th we cast again.
” And we need about 72 hours for this concrete to set. Therefore, the opening will be on the 28th December midnight, that is 72-hour closure.

Related Keywords

Ojota ,Lagos ,Nigeria ,Cairo ,Al Qahirah ,Egypt ,Oworonsoki ,Oworonshoki ,Ibadan ,Oyo ,Lagos Island ,Ebute Meta ,Julius Berger ,Messers Julius Berger ,Goodluck Jonathan ,News Agency Of Nigeria ,Federal Controller ,Works Lagos ,Third Mainland Bridge ,News Agency ,Island Bound ,Lagos Ibadan Expressway ,Federal Government ,Adeniji Ramp ,Apapa Oshodi Expressway ,Adeniji Adele Interchange ,President Goodluck Jonathan ,Sagamu Interchange ,லாகோஸ் ,நைஜீரியா ,கெய்ரோ ,எகிப்து ,ஓயோ ,லாகோஸ் தீவு ,ஜூலியஸ் பெர்கர் ,செய்தியாளர்கள் ஜூலியஸ் பெர்கர் ,குட்லக் ஜொனாதன் ,கூட்டாட்சியின் கட்டுப்படுத்தி ,வேலை செய்கிறது லாகோஸ் ,மூன்றாவது பிரதான நிலப்பரப்பு பாலம் ,தீவு பிணைக்கப்பட்டுள்ளது ,கூட்டாட்சியின் அரசு ,ப்ரெஸிடெஂட் குட்லக் ஜொனாதன் ,

© 2025 Vimarsana

comparemela.com © 2020. All Rights Reserved.