CROWN POINTÂ â The Board of Public Works accepted two bids Wednesday for the final leg of the cityâs portion of the 109th Avenue expansion project.
The apparent low bidder on the project, pending review of its documentation, is Rieth-Riley Construction Co. The Gary firm bid $1,097,489.59. The other bidder was Milestone Contractors North Inc. of Griffith, which quoted $1,127,516.77 on the project.
Speaking after the special meeting, Mayor David Uran explained that this final leg of the project covers 109th Avenue from Delaware Parkway eastbound to the Indiana Department of Transportation interchange at I-65. The project, to be completed this year, expands the roadway to a four-lane boulevard.