Hereâs a look at what drivers can expect:
Â
long-term projects
State Route 20: Work continues a $16.8 million project funded in part by Senate Bill 1, the Road Repair and Accountability Act of 2017, to rehabilitate the pavement, widen shoulders and realign the roadway between Loma Rica Road and Spring Valley Road. Project information and construction updates are available at www.FixYuba20.com No traffic-interfering work is scheduled.
State Route 20: Work continues on a $61.5 million project funded in part by Senate Bill 1, the Road Repair and Accountability Act of 2017, to straighten and flatten roadway curves and slopes, widen shoulders, construct a new bridge and rehabilitate a 4.5-mile section of roadway in the Browns Valley area. Construction is expected to be completed in 2021. Project information and construction updates are available at www.FixYuba20.com Project in winter suspension.