Stage one of the project took place in April 2017. Credit: Office of the President, the Republic of Ghana.
The first stage of the 400MW Bridge Power project will be installed with five GE TM2500+ gas turbines. Credit: GE.
Stage two of the project will add 206MW of capacity. Credit: GE.
Bridge Power project is a 400MW liquefied petroleum gas (LPG)-fuelled combined-cycle power plant being developed in Tema, Ghana. The project is the first of its kind to be undertaken in Africa.
The $953m power plant is being built in two phases with the first stage with a capacity of 194MW and the second with a capacity of 206MW.

Related Keywords

Hungary ,Ghana ,Ghanaian , ,Early Power ,Sage Petroleum ,Electricity Corporation Of Ghana ,Clifford Chance ,Bridge Power ,Power Limited ,Endeavor Energy ,Sage Petroleum Limited ,Electricity Corporation ,Jacobs Consultancy ,Associated Consultants ,Kina Advisory ,பசி ,கானா ,ஆரம்ப பவர் ,முனிவர் பெட்ரோலியம் ,மின்சாரம் நிறுவனம் ஆஃப் கானா ,கிளிஃபோர்ட் வாய்ப்பு ,பாலம் பவர் ,பவர் வரையறுக்கப்பட்டவை ,முயற்சி ஆற்றல் ,முனிவர் பெட்ரோலியம் வரையறுக்கப்பட்டவை ,மின்சாரம் நிறுவனம் ,ஜாகோப்ஸ் ஆலோசனை ,தொடர்புடையது ஆலோசகர்கள் ,

© 2025 Vimarsana

comparemela.com © 2020. All Rights Reserved.