A look at road projects in Yuba-Sutter-Colusa [Appeal-Democrat, Marysville, Calif.]
Jan. 16—There’s no shortage of roadwork in the Yuba-Sutter-Colusa region, local and state. Here’s a look at some of the various projects, as reported by local officials: — After months of construction work, Gilbert Mohtes-Chan, public information officer for Caltrans District 3, said work on a $37.7 million project to restore nearly 12 lane miles of pavement on State Route 20 between Lytle Road and the Sutter Bypass, widen the shoulders and replace the Wadsworth Canal Bridge will be completed in just a few weeks.
“Bridge deck surfacing and drainage work on the new Wadsworth Canal Bridge is anticipated this month,” said Mohtes-Chan. — A $61.5 million project on State Route 20 in Yuba County to straighten and flatten roadway curves and slopes, widen shoulders, construct a new bridge and rehabilitate a 4.5-mile section of roadway in the Browns Valley area is expected to be completed later this year but progress has been stalled.