According to Department of Public Works and Highways (DPWH) Sec. Mark A. Villar, the bridge that will link Intramuros and Binondo in the city of Manila “is on track to be completed this 2021 amid [the] present pandemic situation.”
The project had initially been penciled for completion in September 2021, but the slight delay has pushed the date further into the fourth quarter of this year.
The DPWH said the project’s current progress rate is about 60 percent.
“The implementing office DPWH Unified Project Management Office – Roads Management Cluster 1 (UPMO-RMC 1) and contractor China Road and Bridge Corporation have made efforts to speed up work progress to ensure that the P3.39-billion project will be completed by this fourth quarter,” Villar said following an inspection on Thursday, April 15.
Binondo-Intramuros Bridge seen completed within 2021
radyonatin.com - get the latest breaking news, showbiz & celebrity photos, sport news & rumours, viral videos and top stories from radyonatin.com Daily Mail and Mail on Sunday newspapers.
Flagship P3 4B Binondo-Intramuros Bridge to be completed within 2021
pakistantelegraph.com - get the latest breaking news, showbiz & celebrity photos, sport news & rumours, viral videos and top stories from pakistantelegraph.com Daily Mail and Mail on Sunday newspapers.