Audubon Group A
After taking a pause during the holidays, Boh Bros Construction Co. crews continued underground utility work and roadway restoration in the Audubon neighborhood as part of the $7.3 million Audubon Group A infrastructure improvement project. In January, crews continued excavation and milling work on Hurst and Octavia streets. Waterline work on Webster and Henry Clay streets continued in close collaboration with Sewerage & Water Board. The project is currently scheduled to be complete in summer 2021, weather permitting.
Black Pearl, East Carrollton Group A
Black Pearl, East Carrollton Group A
The $11.9 million Black Pearl, East Carrollton Group A project, which began construction in August 2020, continues to make progress. In January, Hard Rock Construction Co. completed Americans with Disabilities Act-compliant curb ramps on Burdette, Fern, and Green streets. Waterline and sewer-line work continues on Short and Plum streets. Utility work will continue in the co