North Portsea Island coastal defense update March 17, 2021, by Eldin Ganic
Coastal Partners today released the latest update on their North Portsea Island Coastal Defense Project.
From April to September 2021, they will be constructing the first 500m of seawall and rebuilding two slipways along the Eastern Road as part of the North Portsea Island coastal defense scheme.
“We will also be preparing the area of the next 1km of frontage ready for construction in 2022. The coastal path will be closed with a diversion for pedestrians in place,” the statement reads.
Coastal Partners photo
The North Portsea Island Scheme covers 8.4km of Portsmouth’s coastline from Tipner through to Milton.