Preparing the DPR for the old bridges shall take around three to four months, another 2-3 months for tendering process, and another 12 months for restoration work to be carried out, the AAG stated.
According to the petitioner, the two bridges are in dilapidated condition and the traffic of Gondal and surrounding villages passes through the bridge.
A hearing was held in the Gujarat High Court on Tuesday on a petition filed regarding the dilapidated condition of two heritage sites in Gondal. During | BLiTZ