Glenwood Springs to spend additional $740,000 on South Bridge design postindependent.com - get the latest breaking news, showbiz & celebrity photos, sport news & rumours, viral videos and top stories from postindependent.com Daily Mail and Mail on Sunday newspapers.
A significant portion of the South Midland Avenue project could be paved by the first week of October, Gould Construction Superintendent Dave Metrovich said.
Beginning today, traffic traveling through the roundabout under construction at 4 Mile Road and South Midland Avenue will be single-lane only for the next two weeks, a Glenwood Springs news release states.
Drivers should expect extended lane closures along South Midland seven days a week, according to Bryana Starbuck, Glenwood Springs public information officer.
South Midland motorists should plan for lane closures Mondays through Fridays from 9 a.m. to 4 p.m. and Saturdays through Sundays from 8 a.m. to 6 p.m.
In an email, Starbuck said the South Midland project is generally tracking well.
The rebuilding of the South Midland Avenue corridor is an 18-month reconstruction project. Construction started in 2020 and is expected to wrap up in summer of 2020.
This stretch of roadway is prone to potholes, intersections have poor sight lines, the corridor experiences regular rockfall events and there are gaps in pedestrian infrastructure and traffic volumes are on the rise. Approximately one-third of Glenwood Springs residents use this corridor. Global supply chain issues have been a challenge across projects,” she said. “With the work schedule over the next six weeks, construction cre
Glenwood Springs drivers can expect lane closures in South Midland Avenue construction zone until early summer postindependent.com - get the latest breaking news, showbiz & celebrity photos, sport news & rumours, viral videos and top stories from postindependent.com Daily Mail and Mail on Sunday newspapers.