Rio Tinto s expansion of Oyu Tolgoi to kick off in late 2022

Rio Tinto’s $6.7bn Oyu Tolgoi expansion to begin in 2022 Rio Tinto has said the underground expansion of Oyu Tolgoi is its most important growth project ( Rio Tinto (ASX, LON, NYSE:RIO) unveiled on Wednesday that underground production from the Oyu Tolgoi copper-gold mine in Mongolia is slated to begin in October 2022, adding that it will come with a price tag of $6.75 billion. When it was approved in 2015, Rio expected the expansion to cost $5.3 billion and reach its first sustainable production in early 2021. Sign Up for the Copper Digest Sign Up Last year, however, the company flagged stability risks associated with the original project design, which translated into as much as an additional $1.9 billion cost. Expected production was then moved to between October 2022 and July 2023.