Commissioners approved the lowest bid.
Fenner said the work on the bridge is scheduled to start about the middle of May after the Sweet Springs R-7 school year ends. He said the estimated duration of the project was thought to be about 70 days. But he was informed by the construction company’s owner that it could take as long as 90 days to complete.
There has been a slight delay in some of the work related to the waterline for the project at Marshall Junction, but it shouldn’t be a big factor.
During the Saline County Commission meeting on Tuesday, January 26, Southern District Commissioner Monte Fenner explained the workers did not start work near Route H (Boat Road) as they expected to do late last week.