Los Alamos lab may face greater demand for plutonium pits
by
(Tribune News Service) The plutonium pit factory at Savannah River Site in South Carolina will take years longer and cost billions of dollars more to ramp up than previously planned, which could push Los Alamos National Laboratory to make more nuclear bomb cores to fill the gap, watchdog groups say.
For the past three years, plans have called for the Los Alamos lab to produce 30 plutonium warhead triggers by 2026 and Savannah River to make 50 by 2030, but the latter is proving much more costly and nettlesome than anticipated.
Jill Hruby, the nominee to head the National Nuclear Security Administration, said in a U.S. Senate hearing last week that Savannah River might not fully operate until 2035.