2020 was the “single greatest year” for capital project execution in Reston Association’s history, outgoing RA president Julie Bitzer declared at the association’s annual members’ meeting on Tuesday (April 13).
However, a number of much-needed capital projects remain, and RA CEO Hank Lynch says the ability to fund them is “primarily my biggest concern” for the next five to 10 years.
Despite delays and shortages related to the ongoing COVID-19 pandemic, Reston Association managed to finish 85 of its 121 ongoing capital projects this past year 70% completion rate.
There are 13 active projects, and 28 projects will be completed this coming year, according to the map available on RA’s website.
Lake Thoreau Pool Preliminary Site Plan Heading for Design Review Board restonnow.com - get the latest breaking news, showbiz & celebrity photos, sport news & rumours, viral videos and top stories from restonnow.com Daily Mail and Mail on Sunday newspapers.
March 1, 2021 at 11:00am
The major renovation of Lake Thoreau Pool, which has been closed since last year, is set for a groundbreaking in October.
While the project is on budget, the overall effort is roughly three months behind schedule due to the impact of the COVID-19 pandemic and anticipated delays with the county’s permitting process.
In a presentation to Reston Association’s Board of Directors late last week, Chris Schumaker, RA’s capital projects director, said that while it may be possible to catch up on the project timeline, permitting delays are very common due to the pandemic.
“Things that used to take weeks now take months,” Schumaker said.
January 28, 2021 at 2:30pm
Lake Audubon Pool, operated by Reston Association, is in the midst of renovations. The pool is undergoing re-plastering, the pump and filter are being replaced, and other plumbing is being fixed.
Work began in mid-January and is expected to be completed sometime between mid-April and early May. But weather could delay the project, cautions Mike Leone of Reston Association.
This week work on the Lake Audubon Pool capital project began. This project will involve a full removal (pictured) and re-plaster of the pool, as well as replacing the pool pump, filter, and associated plumbing in totality. The project will be completed by mid to late April. pic.twitter.com/AO40Nul3Ps