To view and print a detailed list of closures and detours CLICK HERE!
REMINDER! Fairview Road Bridge Partial Demolition
Crews shifted traffic to the new side of the Fairview bridge over I-405 on Friday, Feb. 12, in anticipation of partial demolition.
Demolition activities have begun and the second half of the bridge will continue to be demolished over one more night under full freeway closures. Additional nighttime demolition will occur for several weeks under freeway lane closures. Some daytime demolition also is anticipated.
Night Three
Lane reductions will be in place from 7 to 8 a.m. Saturday, March 6
Fairview Road closure from 10 p.m. Friday, March 5, to 8 a.m. Saturday, March 6
I-405 Improvement Project construction alert: Week of February 22 oc-breeze.com - get the latest breaking news, showbiz & celebrity photos, sport news & rumours, viral videos and top stories from oc-breeze.com Daily Mail and Mail on Sunday newspapers.
To view and print a detailed list of closures and detours CLICK HERE!
UPDATE! Full Southbound (SB) and Northbound (NB) Freeway Closures for Edwards Street Falsework Installation
Crews will begin constructing falsework for the Edwards Street bridge over I-405 in early-February. This work requires full freeway closures of NB and SB I-405 between Bolsa Avenue and Westminster Boulevard.
The SB freeway closures are set for 10 p.m. to 5 a.m.:
Monday, Feb. 8 through Thursday, Feb. 11 and Tuesday, Feb. 16
The NB freeway closures are set for 10 p.m. to 5 a.m.:
Tuesday, Feb. 16 through Friday, Feb. 19
Monday, Feb. 22,
Sign up for project-wide and bridge-specific construction alerts at bit.ly/405-signup.
NB nightly full freeway closures are set to continue 10 p.m. to 5:30 a.m.:
Thursday, Jan. 28
Monday, Feb. 1 through Thursday, Feb. 4 Only one direction is planned to be closed. If SB work has not been completed, it will be closed. Otherwise, northbound (NB) will be closed.
REMINDER! Nightly Southbound (SB) I-405 Freeway Closures for Bridge Work
Nightly SB I-405 closures are scheduled to continue for Brookhurst Street bridge construction. Activities include equipment mobilization, pile installation, shoring installation, falsework installation and grading, and column demolition for the old half of the Brookhurst bridge.
SB I-405 will be closed between Magnolia and Brookhurst.
SB nightly full freeway closures are set for 10 p.m. to 5:30 a.m.:
Monday, Jan. 18 through Friday, Jan. 22
Monday, Jan. 25
Tuesday, Jan. 26 Only one direction is planned to be closed. If SB work has not been completed, it will be closed. Otherwise, northbound (NB) will be closed.
Sign up for project-wide and bridge-specific construction alerts at bit.ly/405-signup.
NEW! Northbound (NB) and Southbound (SB) I-405 Freeway Lane Reductions for Pile Installation
Crews will close the inside lanes on the SB and NB I-405 between Beach Boulevard and Newland Street for approximately one month to advance pile installation activities for the Edinger Avenue bridge.