ORANGE Following hesitation about putting an obsolete piece of military equipment on display in Memorial Park, the Selectboard’s representative for the Trustees of Soldiers Memorial has agreed to approach his fellow American Legion members about.
Design must stabilize glacial till for Fisher Hill school expansion in Orange
Glacial till was discovered where there was expected to be ledge and engineers will have to devise a way to stabilize it while building an access road to Fisher Hill Elementary School that will serve as a second entry and exit route. STAFF PHOTO/PAUL FRANZ
Modified: 2/24/2021 2:46:15 PM
ORANGE The Fisher Hill Elementary School project’s $45.7 million construction cost is expected to remain under budget after engineers devise a way to stabilize the glacial till so it doesn’t slide into the planned new school access road.
Martin Goulet of Hill International Inc., the company managing the project on behalf of the town, said an unforeseen issue arose when crew members cut into a hill. Glacial till was discovered where there was expected to be ledge. This means Raymond Design Associates, the architecture firm handling the project, must design the access road in a way that does not allow the till to s
The Recorder - Design must stabilize glacial till for Fisher Hill school expansion in Orange recorder.com - get the latest breaking news, showbiz & celebrity photos, sport news & rumours, viral videos and top stories from recorder.com Daily Mail and Mail on Sunday newspapers.
Bingo World in Cape Girardeau to reopen
Bingo World in Cape Girardeau to reopen By Jeremy Ford | February 4, 2021 at 5:06 PM CST - Updated February 4 at 6:26 PM
CAPE GIRARDEAU, Mo. (KFVS) - Friday nights will be a little bit more fun for seniors starting on Friday, February 5 as Bingo World is set to reopen.
The non-profit fundraising facility has made changes on the inside, but it still gives the public a chance to win thousands of dollars.
Bingo is one of the most popular games played throughout the senior community. And after being shut down due to COVID-19, this Friday night hotspot is ready to reopen.
Orange’s Fisher Hill Elementary School design phase reaches 60% milestone
The Fisher Hill Elementary School project’s design phase is 60 percent complete. FISHER HILL SCHOOL CONSTRUCTION FACEBOOK PAGE
The Fisher Hill Elementary School project’s design phase is 60 percent complete. COURTESY PHOTO/FISHER HILL SCHOOL CONSTRUCTION FACEBOOK PAGE
This is what the new Fisher Hill Elementary School would look like with a three-story addition built onto its northern side. CONTRIBUTED IMAGE
Published: 2/1/2021 5:51:22 PM
ORANGE The Fisher Hill Elementary School project’s design phase has reached 60 percent completion, and the town expects to award a construction contract at the end of June.