Simpson Bay:--- There have already been some substantial positive environmental updates due to the discarding of massive volumes of debris and waste during the pre-works of the Airport Terminal Reconstruction Project. The debris and waste, as a result of Hurricane Irma, was diverted from entering the local landfill in the capital of the country, from the Mold Remediation and Waste Disposal Management Works.
This pre-work was remediated in the basement, the former check-in hall, the departure hall level 1, and PJIAE executive spaces on level 2 of the Princess Juliana International Airport Terminal Building (SXM).
Reports from the Project Management Unit (PMU) confirmed that the waste was systematically separated and delivered to both local and international facilities. Through the diverse waste streams, the debris materials were then transported abroad for further recycling or disposal. The sorted waste is comprised of metals (ferrous and non-ferrous), glass, E-Waste, concrete, and more.

Related Keywords

Mirto Breell , National Recovery Project Bureau , Princess Juliana International Airport Terminal Building , World Bank , European Investment Bank , Departure Hall , Airport Terminal Reconstruction , Hurricane Irma , Mold Remediation , Waste Disposal Management , Project Management Unit , Terminal Building , Social Commitment Plan , General Contractor , Airport Terminal Reconstruction Project , On Lending Agreements , Sint Maarten , தேசிய மீட்பு ப்ராஜெக்ட் பணியகம் , ப்ரிந்ஸெஸ் ஜூலியானா சர்வதேச விமான முனையத்தில் கட்டிடம் , உலகம் வங்கி , ஐரோப்பிய முதலீடு வங்கி , புறப்பாடு மண்டபம் , விமான முனையத்தில் புனரமைப்பு , சூறாவளி இர்மா , அச்சு பரிகாரம் , ப்ராஜெக்ட் மேலாண்மை அலகு , முனையத்தில் கட்டிடம் , சமூக அர்ப்பணிப்பு திட்டம் , ஜநரல் ஒப்பந்தக்காரர் , விமான முனையத்தில் புனரமைப்பு ப்ராஜெக்ட் , சிந்ட் மார்டன் ,

© 2024 Vimarsana

comparemela.com © 2020. All Rights Reserved.