Ghaziabad: The National Capital Region Transport Corporation (NCRTC) is likely to start laying tracks on the Sahibabad-Duhai stretch for the Regional Rapid Rail Transit System by next week. The 17km-stretch is a priority section and has a deadline of 2023.
“The railway tracks have reached the construction site. An 8km-long viaduct on the priority section is ready and the work to lay the tracks is expected to start by next week,” said Puneet Vats, chief public relations officer, NCRTC.
The corporation is also preparing a draft for a value capture funding model along the 82km-long RRTS corridor. Officials said it is likely to be ready in about 20 days and after that, it will be sent to the state cabinet for approval.

Related Keywords

Meerut ,Uttar Pradesh ,India ,Ghaziabad ,Asheesh Shivpuri ,Sarai Kale Khan ,Ghaziabad Development Authority ,National Capital Region Transport Corporation ,Regional Rapid Rail Transit System ,Puneet Vats ,மீரட் ,உத்தர் பிரதேஷ் ,இந்தியா ,காஜியாபாத் ,ஆஷீஷ் ஷிவ்புரி ,சாரை காலே காந் ,காஜியாபாத் வளர்ச்சி அதிகாரம் ,தேசிய மூலதனம் பகுதி போக்குவரத்து நிறுவனம் ,பிராந்திய விரைவான ரயில் போக்குவரத்து அமைப்பு ,

© 2024 Vimarsana

comparemela.com © 2020. All Rights Reserved.