Centerm expansion project – March update
March 8, 2021,
by
Zlatan Hrvacevic
The Vancouver Fraser Port Authority, together with their contractors, is continuing work on the Centerm Expansion Project.
This port expansion project, being delivered by Centennial Expansion Partners (CXP), has completion date of December 2021.
In their March update, CXP and the port authority said that the preload settlement in the eastern expansion area is fully complete. “We are currently moving to infill the area around the perimeter of the original Ballantyne Pier.”
They also added that the infilling and preload placement in the western expansion area was completed in December 2020 and the second phase of preload is ongoing.